Troubleshooting the flotation plant at Danpo, Give

  • Keiding, Kristian, (Projektdeltager)

Projektdetaljer

Beskrivelse

Due to problems with high decharge of N-containing compounds, the entire production plant was monitored in order to identify the source or cause for this high discharge. The discharge was identified to relate to the cleaning of the the production line and specifically to one unit of the plant. Consequential, the cleaning procedure was changed.
StatusAfsluttet
Effektiv start/slut dato19/05/201019/05/2013

Finansiering

  • <ingen navn>