Impact of Cost of Selected Mooring Solutions on CoE of Partner WECs: CM2 & WP5

Kim Nielsen, Jonas Bjerg Thomsen, Francesco Ferri, Erik Friis-Madsen, Kurt Due Rasmussen, Sarah Thomas, Jens Peter Kofoed

Publikation: Bog/antologi/afhandling/rapportRapportForskning

Resumé

The objective of the report is to explain the development of the LCoE for partner WECs due to the new mooring systems developed as part of the MSLWEC project, by comparison of the initial LCoE against LCoE for the solutions found at the end of the project.
OriginalsprogEngelsk
Udgivelses stedAalborg
ForlagDepartment of Civil Engineering, Aalborg University
Antal sider50
StatusUdgivet - 2018
NavnDCE Contract Reports
Nummer197
ISSNuden issn

Emneord

  • Mooring solutions

Citer dette

Nielsen, K., Thomsen, J. B., Ferri, F., Friis-Madsen, E., Rasmussen, K. D., Thomas, S., & Kofoed, J. P. (2018). Impact of Cost of Selected Mooring Solutions on CoE of Partner WECs: CM2 & WP5. Aalborg: Department of Civil Engineering, Aalborg University. DCE Contract Reports, Nr. 197
Nielsen, Kim ; Thomsen, Jonas Bjerg ; Ferri, Francesco ; Friis-Madsen, Erik ; Rasmussen, Kurt Due ; Thomas, Sarah ; Kofoed, Jens Peter. / Impact of Cost of Selected Mooring Solutions on CoE of Partner WECs : CM2 & WP5. Aalborg : Department of Civil Engineering, Aalborg University, 2018. 50 s. (DCE Contract Reports; Nr. 197).
@book{8f545150a13c44b2ae6c982a5d405971,
title = "Impact of Cost of Selected Mooring Solutions on CoE of Partner WECs: CM2 & WP5",
abstract = "The objective of the report is to explain the development of the LCoE for partner WECs due to the new mooring systems developed as part of the MSLWEC project, by comparison of the initial LCoE against LCoE for the solutions found at the end of the project.",
keywords = "Mooring solutions, Mooring solutions",
author = "Kim Nielsen and Thomsen, {Jonas Bjerg} and Francesco Ferri and Erik Friis-Madsen and Rasmussen, {Kurt Due} and Sarah Thomas and Kofoed, {Jens Peter}",
year = "2018",
language = "English",
series = "DCE Contract Reports",
publisher = "Department of Civil Engineering, Aalborg University",
number = "197",
address = "Denmark",

}

Nielsen, K, Thomsen, JB, Ferri, F, Friis-Madsen, E, Rasmussen, KD, Thomas, S & Kofoed, JP 2018, Impact of Cost of Selected Mooring Solutions on CoE of Partner WECs: CM2 & WP5. DCE Contract Reports, nr. 197, Department of Civil Engineering, Aalborg University, Aalborg.

Impact of Cost of Selected Mooring Solutions on CoE of Partner WECs : CM2 & WP5. / Nielsen, Kim; Thomsen, Jonas Bjerg; Ferri, Francesco; Friis-Madsen, Erik; Rasmussen, Kurt Due; Thomas, Sarah; Kofoed, Jens Peter.

Aalborg : Department of Civil Engineering, Aalborg University, 2018. 50 s. (DCE Contract Reports; Nr. 197).

Publikation: Bog/antologi/afhandling/rapportRapportForskning

TY - RPRT

T1 - Impact of Cost of Selected Mooring Solutions on CoE of Partner WECs

T2 - CM2 & WP5

AU - Nielsen, Kim

AU - Thomsen, Jonas Bjerg

AU - Ferri, Francesco

AU - Friis-Madsen, Erik

AU - Rasmussen, Kurt Due

AU - Thomas, Sarah

AU - Kofoed, Jens Peter

PY - 2018

Y1 - 2018

N2 - The objective of the report is to explain the development of the LCoE for partner WECs due to the new mooring systems developed as part of the MSLWEC project, by comparison of the initial LCoE against LCoE for the solutions found at the end of the project.

AB - The objective of the report is to explain the development of the LCoE for partner WECs due to the new mooring systems developed as part of the MSLWEC project, by comparison of the initial LCoE against LCoE for the solutions found at the end of the project.

KW - Mooring solutions

KW - Mooring solutions

M3 - Report

T3 - DCE Contract Reports

BT - Impact of Cost of Selected Mooring Solutions on CoE of Partner WECs

PB - Department of Civil Engineering, Aalborg University

CY - Aalborg

ER -

Nielsen K, Thomsen JB, Ferri F, Friis-Madsen E, Rasmussen KD, Thomas S et al. Impact of Cost of Selected Mooring Solutions on CoE of Partner WECs: CM2 & WP5. Aalborg: Department of Civil Engineering, Aalborg University, 2018. 50 s. (DCE Contract Reports; Nr. 197).