Learning to see value-adding and non-value-adding work time in renovation production systems

Hasse Neve*, Søren Wandahl, Søren Lindhard, Jochen Teizer, Jon Lerche

*Kontaktforfatter

Publikation: Bidrag til tidsskriftTidsskriftartikelForskningpeer review

1 Citationer (Scopus)
6 Downloads (Pure)

Abstrakt

For decades construction labour productivity has been stagnated or declining. Changing this issue requires new knowledge on the labour-intensive construction production system. The work sampling method was applied to collect data from three renovation construction production systems. It quantifies observations of on-site work and enables deep analyses of how time is used. The analysis revealed that the renovation projects had a baseline of value-adding-work (VAW) time on 29.5%. It further identified five system behaviours outlining how VAW and Non-Value-Adding work (NVAW) time behaves. The new knowledge of how both VAW and NVAW time behaves advances knowledge on how time is wasted in construction projects and opens new branches of future research. The findings are furthermore of potential use to industry professionals who work with process improvement in renovation projects because they provide, among others, answers to how targets can be defined for both VAW and NVAW.
OriginalsprogEngelsk
TidsskriftProduction Planning and Control
ISSN0953-7287
DOI
StatusE-pub ahead of print - 9 nov. 2020

Bibliografisk note

Publisher Copyright:
© 2020 Informa UK Limited, trading as Taylor & Francis Group.

Copyright:
Copyright 2020 Elsevier B.V., All rights reserved.

Fingeraftryk

Dyk ned i forskningsemnerne om 'Learning to see value-adding and non-value-adding work time in renovation production systems'. Sammen danner de et unikt fingeraftryk.

Citationsformater