On the road to improved scheduling - fitting activities to capacity

Søren Munch Lindhard, Søren Wandahl

Publikation: Bidrag til bog/antologi/rapport/konference proceedingKonferenceartikel i proceedingForskningpeer review

Resumé

Last Planner System has through the sounding process increased the reliability of the schedule. The sound activities are moved to a buffer and afterwards selected to the Weekly Work Plans to match capacity. Therefore, in order to maximise productivity it is essential to ensure that the sounding process proceeds in a pace which ensures that enough activities are made ready to the Weekly Work Plans. Experiences from case studies are included. It is observed that site-mangers tend to either include at risk activities or to adjust the manning in order to mach work with capacity. Several different solutions to the problem are suggested and discussed. It is proposed to simplify the production by decreasing the number of trades and tasks completed at site. This can be achieved by increasing
OriginalsprogEngelsk
TitelProceedings of RICS COBRA 2012 Conference
RedaktørerDean Kashiwagi, Kenneth Sullivan
Antal sider9
Udgivelses stedLas Vegas, Nevada USA
Publikationsdato10 sep. 2012
Sider1604-1612
ISBN (Trykt)978-1-84219-840-7
StatusUdgivet - 10 sep. 2012
BegivenhedRICS COBRA 2012 Conference - Las Vegas, USA
Varighed: 11 sep. 201213 sep. 2012

Konference

KonferenceRICS COBRA 2012 Conference
LandUSA
ByLas Vegas
Periode11/09/201213/09/2012

Citer dette

Lindhard, S. M., & Wandahl, S. (2012). On the road to improved scheduling - fitting activities to capacity. I D. Kashiwagi, & K. Sullivan (red.), Proceedings of RICS COBRA 2012 Conference (s. 1604-1612). Las Vegas, Nevada USA.
Lindhard, Søren Munch ; Wandahl, Søren. / On the road to improved scheduling - fitting activities to capacity. Proceedings of RICS COBRA 2012 Conference. red. / Dean Kashiwagi ; Kenneth Sullivan. Las Vegas, Nevada USA, 2012. s. 1604-1612
@inproceedings{454eeb9b986845b9a925cd086ea835fd,
title = "On the road to improved scheduling - fitting activities to capacity",
abstract = "Last Planner System has through the sounding process increased the reliability of the schedule. The sound activities are moved to a buffer and afterwards selected to the Weekly Work Plans to match capacity. Therefore, in order to maximise productivity it is essential to ensure that the sounding process proceeds in a pace which ensures that enough activities are made ready to the Weekly Work Plans. Experiences from case studies are included. It is observed that site-mangers tend to either include at risk activities or to adjust the manning in order to mach work with capacity. Several different solutions to the problem are suggested and discussed. It is proposed to simplify the production by decreasing the number of trades and tasks completed at site. This can be achieved by increasing",
author = "Lindhard, {S{\o}ren Munch} and S{\o}ren Wandahl",
year = "2012",
month = "9",
day = "10",
language = "English",
isbn = "978-1-84219-840-7",
pages = "1604--1612",
editor = "Dean Kashiwagi and Kenneth Sullivan",
booktitle = "Proceedings of RICS COBRA 2012 Conference",

}

Lindhard, SM & Wandahl, S 2012, On the road to improved scheduling - fitting activities to capacity. i D Kashiwagi & K Sullivan (red), Proceedings of RICS COBRA 2012 Conference. Las Vegas, Nevada USA, s. 1604-1612, RICS COBRA 2012 Conference, Las Vegas, USA, 11/09/2012.

On the road to improved scheduling - fitting activities to capacity. / Lindhard, Søren Munch; Wandahl, Søren.

Proceedings of RICS COBRA 2012 Conference. red. / Dean Kashiwagi; Kenneth Sullivan. Las Vegas, Nevada USA, 2012. s. 1604-1612.

Publikation: Bidrag til bog/antologi/rapport/konference proceedingKonferenceartikel i proceedingForskningpeer review

TY - GEN

T1 - On the road to improved scheduling - fitting activities to capacity

AU - Lindhard, Søren Munch

AU - Wandahl, Søren

PY - 2012/9/10

Y1 - 2012/9/10

N2 - Last Planner System has through the sounding process increased the reliability of the schedule. The sound activities are moved to a buffer and afterwards selected to the Weekly Work Plans to match capacity. Therefore, in order to maximise productivity it is essential to ensure that the sounding process proceeds in a pace which ensures that enough activities are made ready to the Weekly Work Plans. Experiences from case studies are included. It is observed that site-mangers tend to either include at risk activities or to adjust the manning in order to mach work with capacity. Several different solutions to the problem are suggested and discussed. It is proposed to simplify the production by decreasing the number of trades and tasks completed at site. This can be achieved by increasing

AB - Last Planner System has through the sounding process increased the reliability of the schedule. The sound activities are moved to a buffer and afterwards selected to the Weekly Work Plans to match capacity. Therefore, in order to maximise productivity it is essential to ensure that the sounding process proceeds in a pace which ensures that enough activities are made ready to the Weekly Work Plans. Experiences from case studies are included. It is observed that site-mangers tend to either include at risk activities or to adjust the manning in order to mach work with capacity. Several different solutions to the problem are suggested and discussed. It is proposed to simplify the production by decreasing the number of trades and tasks completed at site. This can be achieved by increasing

M3 - Article in proceeding

SN - 978-1-84219-840-7

SP - 1604

EP - 1612

BT - Proceedings of RICS COBRA 2012 Conference

A2 - Kashiwagi, Dean

A2 - Sullivan, Kenneth

CY - Las Vegas, Nevada USA

ER -

Lindhard SM, Wandahl S. On the road to improved scheduling - fitting activities to capacity. I Kashiwagi D, Sullivan K, red., Proceedings of RICS COBRA 2012 Conference. Las Vegas, Nevada USA. 2012. s. 1604-1612