The Relation between Pre-planning, Commissioning and Enhanced Project Performance

Bidragets oversatte titel: Relationen mellem tidlig planlægning, idræftsætning og forbedret projektperformance

Publikation: Bidrag til tidsskriftTidsskriftartikelForskningpeer review

71 Downloads (Pure)

Resumé

Pre-planning of construction projects is important for the performance of cost, time, and quality. However, recent research finds that quality related to final testing, adjustment, and balancing of HVAC systems are often overlooked due to deadline pressure. Consequently, this results in poor energy performance and dissatisfied end-users. The purpose of this study is to investigate the relationship between pre-planning, commissioning, and project performance. A publicly funded project with a compressed construction period was followed as a case study. During the case study, passive observation, semi-constructed interviews, and questionnaires were applied. This study showed that by implementing commissioning, project
pre-planning and organizational support is increased. Moreover, the commissioning process creates awareness and fosters proactivity between the project participants, thus complications
are discovered and handled earlier. By improved pre-planning and organizational support, and increasing proactivity, the project’s cost, time and quality performance is improved. This underlines the importance of prioritizing pre-planning. Moreover, increased energy and technical demands increase project complexity which makes project success even more dependent on the quality of the plans.
OriginalsprogEngelsk
Artikelnummer1
TidsskriftConstruction Economics and Building
Vol/bind18
Udgave nummer2
Antal sider14
ISSN2204-9029
DOI
StatusUdgivet - 30 jun. 2018

Emneord

  • Construction management
  • pre-planning
  • commissioning
  • project performance

Citer dette

@article{63cc559d03b4416aaa0ccebe34bdeeaa,
title = "The Relation between Pre-planning, Commissioning and Enhanced Project Performance",
abstract = "Pre-planning of construction projects is important for the performance of cost, time, and quality. However, recent research finds that quality related to final testing, adjustment, and balancing of HVAC systems are often overlooked due to deadline pressure. Consequently, this results in poor energy performance and dissatisfied end-users. The purpose of this study is to investigate the relationship between pre-planning, commissioning, and project performance. A publicly funded project with a compressed construction period was followed as a case study. During the case study, passive observation, semi-constructed interviews, and questionnaires were applied. This study showed that by implementing commissioning, projectpre-planning and organizational support is increased. Moreover, the commissioning process creates awareness and fosters proactivity between the project participants, thus complicationsare discovered and handled earlier. By improved pre-planning and organizational support, and increasing proactivity, the project’s cost, time and quality performance is improved. This underlines the importance of prioritizing pre-planning. Moreover, increased energy and technical demands increase project complexity which makes project success even more dependent on the quality of the plans.",
keywords = "Construction management, pre-planning, commissioning, project performance",
author = "Larsen, {Jesper Kranker} and Lindhard, {S{\o}ren Munch} and Brun{\o}, {Thomas Ditlev} and Jensen, {Kim N{\o}rgaard}",
year = "2018",
month = "6",
day = "30",
doi = "10.5130/AJCEB.v18i2.5762",
language = "English",
volume = "18",
journal = "Construction Economics and Building",
issn = "2204-9029",
publisher = "UTS ePRESS (University of Technology Sydney)",
number = "2",

}

TY - JOUR

T1 - The Relation between Pre-planning, Commissioning and Enhanced Project Performance

AU - Larsen, Jesper Kranker

AU - Lindhard, Søren Munch

AU - Brunø, Thomas Ditlev

AU - Jensen, Kim Nørgaard

PY - 2018/6/30

Y1 - 2018/6/30

N2 - Pre-planning of construction projects is important for the performance of cost, time, and quality. However, recent research finds that quality related to final testing, adjustment, and balancing of HVAC systems are often overlooked due to deadline pressure. Consequently, this results in poor energy performance and dissatisfied end-users. The purpose of this study is to investigate the relationship between pre-planning, commissioning, and project performance. A publicly funded project with a compressed construction period was followed as a case study. During the case study, passive observation, semi-constructed interviews, and questionnaires were applied. This study showed that by implementing commissioning, projectpre-planning and organizational support is increased. Moreover, the commissioning process creates awareness and fosters proactivity between the project participants, thus complicationsare discovered and handled earlier. By improved pre-planning and organizational support, and increasing proactivity, the project’s cost, time and quality performance is improved. This underlines the importance of prioritizing pre-planning. Moreover, increased energy and technical demands increase project complexity which makes project success even more dependent on the quality of the plans.

AB - Pre-planning of construction projects is important for the performance of cost, time, and quality. However, recent research finds that quality related to final testing, adjustment, and balancing of HVAC systems are often overlooked due to deadline pressure. Consequently, this results in poor energy performance and dissatisfied end-users. The purpose of this study is to investigate the relationship between pre-planning, commissioning, and project performance. A publicly funded project with a compressed construction period was followed as a case study. During the case study, passive observation, semi-constructed interviews, and questionnaires were applied. This study showed that by implementing commissioning, projectpre-planning and organizational support is increased. Moreover, the commissioning process creates awareness and fosters proactivity between the project participants, thus complicationsare discovered and handled earlier. By improved pre-planning and organizational support, and increasing proactivity, the project’s cost, time and quality performance is improved. This underlines the importance of prioritizing pre-planning. Moreover, increased energy and technical demands increase project complexity which makes project success even more dependent on the quality of the plans.

KW - Construction management

KW - pre-planning

KW - commissioning

KW - project performance

U2 - 10.5130/AJCEB.v18i2.5762

DO - 10.5130/AJCEB.v18i2.5762

M3 - Journal article

VL - 18

JO - Construction Economics and Building

JF - Construction Economics and Building

SN - 2204-9029

IS - 2

M1 - 1

ER -