Abstract
This report has been prepared by Per Resen and Aalborg University for the ForskVE project 10878: 2 kW grid connected LOPF test buoy. AAU has the role of reviewing and advise on the data analysis, besides compiling this report.
The purpose of this project was to document the mechanical power production against a target power curve of a 2kW grid connected wave energy buoy in Nissum Bredning at Helligsø.
The purpose of this project was to document the mechanical power production against a target power curve of a 2kW grid connected wave energy buoy in Nissum Bredning at Helligsø.
Originalsprog | Engelsk |
---|
Udgivelsessted | Aalborg |
---|---|
Forlag | Department of Civil Engineering, Aalborg University |
Antal sider | 30 |
Status | Udgivet - 2017 |
Navn | DCE Technical reports |
---|---|
Nummer | 231 |
ISSN | 1901-726X |
Emneord
- Wave energy
- Power take-off
- Nissum Bredning
Fingeraftryk
Dyk ned i forskningsemnerne om 'Review of 2 kW grid connected LOPF tests in Nissum Bredning'. Sammen danner de et unikt fingeraftryk.Presse/Medier
-
Klar med nyt bølgeanlæg: Har lært af fortidens fejl
Lucia Margheritini
08/10/2017
2 elementer af Mediedækning
Presse/medie