Abstract
Original language | English |
---|
Place of Publication | Aalborg |
---|---|
Publisher | Department of Civil Engineering, Aalborg University |
Number of pages | 26 |
Publication status | Published - 2017 |
Series | DCE Contract Reports |
---|---|
Number | 187 |
ISSN | uden issn |
Fingerprint
Keywords
- Wave energy
- Power take-off
- Nissum Bredning
Cite this
}
Test Plan for WEPTOS #1 : Prototype in Brandsø. / Margheritini, Lucia; Tetu, Amélie; Ferri, Francesco; Kofoed, Jens Peter; Sonalier, Nathan.
Aalborg : Department of Civil Engineering, Aalborg University, 2017. 26 p. (DCE Contract Reports; No. 187).Research output: Book/Report › Report › Research
TY - RPRT
T1 - Test Plan for WEPTOS #1
T2 - Prototype in Brandsø
AU - Margheritini, Lucia
AU - Tetu, Amélie
AU - Ferri, Francesco
AU - Kofoed, Jens Peter
AU - Sonalier, Nathan
PY - 2017
Y1 - 2017
N2 - This report presents the test program for the WEPTOS Prototype in Brandsø and should be used during testing in order to prioritize and implement the selected configurations to be tested in the available time frame. One configuration is characterized by a defined combination of device opening angle and control strategy.
AB - This report presents the test program for the WEPTOS Prototype in Brandsø and should be used during testing in order to prioritize and implement the selected configurations to be tested in the available time frame. One configuration is characterized by a defined combination of device opening angle and control strategy.
KW - Wave energy
KW - Power take-off
KW - Nissum Bredning
KW - Wave energy
KW - Power take-off
KW - Nissum Bredning
M3 - Report
T3 - DCE Contract Reports
BT - Test Plan for WEPTOS #1
PB - Department of Civil Engineering, Aalborg University
CY - Aalborg
ER -